Until mid-May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Graduate College accommodation. From Friday 6 March until mid-May 2026, the contractor will then be working on the connection of the external pipework into plant rooms on the top floor of House 16 Loweswater and House 19 Stickle.
House 7 Crummock Water
External pipework installation: 27 April – end of April
House 8 Derwentwater
External pipework installation: 5 May – early May
Core hole: 6 May
Internal pipework installation: 6 May
House 9 Devoke
External pipework installation: 5 May – mid-May
Core hole: 6-12 May
Internal pipework installation: 6 May – mid-May
House 11 Ennerdale
External pipework installation: 20 April – late April
Core hole: 20 April
Internal pipework installation: 20 April
House 16 Loweswater
Internal plant room connections: 27 March – end of April
Internal access for system commissioning: 20 April and 7 May
House 19 Stickle
Internal plant room connections: 7 April – 19 May
Internal access for system commissioning: 22 April
- Scaffolding will be erected or high-level access machinery will be used to allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plant room connection works Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Cartmel College accommodation
Until mid-May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Cartmel College accommodation. From Friday 20 March until September 2026, the contractor will then be working on the connection of the external pipework into plant rooms on the top floor of the houses.
House 20 Thirlmere
Internal plant room connections: 6 May – 10 September
Internal access for system commissioning: 28 April
House 46 Bigland
External pipework installation: 16 March – mid-April
Internal plant room connections: 7 April – early May
Core hole: 16 April
House 52 Haverthwaite
External pipework installation: 30 March – end of April
Internal plant room connections: 14 April – early May
Core hole: 16 April
House 54 Grange
External pipework installation: 15 April – mid-May
Internal plant room connections: 20 April – early May
House 55 Braystones Tarn
Internal access for system commissioning: 6 May
- Scaffolding will be erected or high-level access machinery will be used at one side of each building. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plant room connection works Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
Cartmel family flats and houses
From 7 April until early May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the external district heating pipework to Graduate College - Cartmel family flats and houses. Vital Energi contractors will be installing external pipework only at this time, in readiness for summer internal connections.
Houses 158 – 162 Lyth
External pipework installation: 7 April – mid-April
Houses 163 – 168 Backbarrow
External pipework installation: 13 April – late April
Houses 169 – 171 Hayeswater
External pipework installation: 20 April – end of April
Houses 172 – 179 Seathwaite
External pipework installation: 27 April – early May
Encasement work to risers (all spaces): 8 May – early July
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Until the end of April 2026, the Net Zero Energy Project contractor will be working on the connection of the external district heating pipework into plant rooms at Pendle College accommodation.
House 21 Ullswater
Internal access for system commissioning: 29 April
House 24 Winewall
Internal access for system commissioning: 23 April
House 27 Crowtrees
Internal plant room connections: 27 March – end of April
Internal access for system commissioning: 27 April
- Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Until July 2026, the Net Zero Energy Project contractor will be working on the connection of the external district pipework into plant rooms at Lonsdale College accommodation.
House 34 Whittington
Internal access for system commissioning: 21 April
House 36 Tunstall
Internal plant room connections: 13 May – early July
House 39 Barbon
Internal access for system commissioning: 20 April
House 40 Casterton
Internal access for system commissioning: 30 April
House 43 Arkholme
Internal plant room connections: 7 April – early May
- Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.